Government Construction Projects We Have Handled
University of Maryland Flood Mitigation, Princess Anne, MD (UMES)
Contract Duration: 180 Days
Completion Date: Client Extension for additional work still ongoing
Role in Project: Sub-Contractor
Scope of Work: Provide and install concrete pump stations and valve vaults at University Terrace, Frederick Douglass and Student Service Center buildings.
Project Outcome: project ongoing with positive progression from client.
Devil’s Den Rehabilitation Project, Gettysburg, PA (National Park Service)
Contract Duration: 40 Days
Completion Date: 5/2022
Role in Project: Subcontractor
Scope of Work: Provided all labor & equipment services to demolish existing trails, removed tree stump, prepare/form & pour exposed aggregate concrete walkways on trails, installed all turndown concrete foundation for smooth transition, installed granite stone steps, compacted and re-vegetate disturbed areas.
Project Outcome: Completed on time and within the allotted schedule.
Bombay Hook NWR- Various Improvement (U.S Fish & Wildlife Service)
Contract Duration: 100 days
Completion Date: 10/2021
Role in Project: Contractor
Scope of Work: Removed and disposed of the existing guardrail parking system and replace with marine grade 6x6 timbers. Backfilled and compacted site to original elevation.
Project Outcome: Completed on time and within budget. Clients were extremely pleased.
Bombay Hook NWR- Various Improvement (U.S Fish & Wildlife Service)
Contract Duration: 100 days
Completion Date: 10/2021
Role in Project: Contractor
Scope of Work: Installed concrete walkway around vault toilet and re-vegetate disturbed areas.
Project Outcome: Completed ahead of schedule and within budget. Clients were extremely pleased.